The problem
Single-story home with a screened pool enclosure tied into the back of the roof. When we came out on August 7 the roof was already under a tarp to keep water out until it could be replaced, and the old shingles along the enclosure were worn through in spots.
What we did
Everything came off down to the deck on August 17. Bad plywood was cut out and replaced with new sheets (the agreement covered up to ten), and the rest of the deck was re-nailed. Self-adhering ice and water shield went over the whole deck.
Then new white drip edge, IKO Cambridge architectural shingles in Weatherwood and ridge caps. Three new pipe boots and a zipper boot went in, and the old ones went in the dumpster.
Before and after


Start to finish
Job photos from our crew, in order.







The result
Finished: August 17, 2026
The finished photos were taken that evening. Tan Weatherwood shingles from the front ridge to the pool enclosure, and no tarp.
Questions homeowners ask about this kind of job
Does roof replacement include decking?
A roof replacement typically includes replacing damaged sections of decking before installing new materials. On this St. Petersburg roof, bad plywood was cut out and replaced with new sheets after stripping the old roof to the deck. The rest of the deck was re-nailed before the underlayment went down.
Is shingle underlayment the same as ice and water shield?
Ice and water shield is a specific self-adhering, waterproof underlayment membrane designed to seal against the roof deck. On this St. Petersburg roof, self-adhering ice and water shield was installed over the whole deck before laying the new white drip edge and IKO Cambridge architectural shingles.